PSEG Service Upgrade: Who Does What, Step by Step

6 min read

Once you know your home needs a bigger electric service, here is what happens next on Long Island: the estimate, the permit, the PSEG Long Island request, work day and the certificate.

You already know the house needs more power. Maybe an electrician looked at the old 100 amp service and said it will not carry the EV charger, the heat pump or the new kitchen. Now the question is what actually happens next, and why PSEG Long Island keeps coming up in the conversation.

A PSEG service upgrade on Long Island involves four parties besides you: your electrician, your town or village building department, an approved inspection agency, and the utility. Each one signs off on a different piece. If you still want the case for upgrading in the first place, our complete guide to electric service upgrades and 200 amp panels covers that. This post is about the order of events.

Why PSEG Long Island is part of your electrical service upgrade

An electrical service upgrade crosses the line between what the utility owns and what you own. PSEG Long Island's Red Book (its Specifications and Requirements for Electric Installations, 2026 edition) splits it this way:

| Equipment | Who owns it |
|---|---|
| Service drop (the overhead wires from the pole to your house) | PSEG Long Island |
| Revenue meter | PSEG Long Island |
| Meter pan (meter mounting equipment) | You |
| Service entrance conductors and riser | You |
| Panel and main breaker (service equipment) | You |

The Red Book also says PSEG Long Island is the only supplier of revenue meters, and contractors may not keep or dispose of them. Because the work touches both sides of that line, the utility has to be involved from the paperwork stage through reconnection.

Step 1: The site visit and written estimate

Everything starts with an electrician looking at what you have now. That means the existing service size, the meter pan, the riser running up the side of the house, the service wire, the panel itself and the grounding.

From there the electrician writes up the service that fits the house and what you plan to add. Common options:

  • A 100 amp meter and riser replacement when the panel is fine but the outside equipment is worn.
  • A 200 amp service upgrade, the most common choice for a single-family home. As listed on our 200 amp service page, that scope includes a 200 amp main breaker panel, a lever bypass meter socket, a PVC riser, copper service wire, a network grounding interface, a water main jumper ground and a ground rod, all installed to local town code.
  • A 320 amp service upgrade for larger homes with heavy loads.
  • A two-family 200 amp service when each unit needs its own meter and panel.

If the panel also has to move, for example out of a finished basement wall or a closet, that is a separate line on the estimate. See panel replacement and relocation.

The estimate should be in writing and spell out the equipment. Read it before you sign anything else.

Step 2: The permit and the inspection agency

Who issues the permit depends on where the house sits.

  • Incorporated villages run their own building departments. The Village of Valley Stream (Village Code Chapter 23) requires a permit application before work starts and an application for a certificate of inspection from an inspection agency approved by the Village. It also requires that all electrical work be done by an electrician currently licensed with the Village. The Village of Lynbrook (Village Code Chapter 112) requires a Building Department permit to increase the existing amperage or add a meter, and a copy of the inspection agency application has to be filed before work starts.
  • Unincorporated areas go through the Town. Under Town of Hempstead Code Chapter 84, professional electrical work needs a Town master electrician's license, and new wiring may not be put in use until a final certificate of compliance is issued by an inspection agency approved by the Town's Examining Board of Electricians (section 84-12). An agency may not inspect work it is affiliated with (section 84-19).

So in each case there are two separate approvals: the permit from the town or village, and the inspection certificate from an approved third-party agency. Before you hire anyone, ask whether the electrician holds a license in your municipality. If you live in or near the village, our page on electrician services in Valley Stream, NY covers the work we do there.

When the electrician files on your behalf, you may be asked to sign an authorization form. Keep an eye on your email so it does not sit unsigned.

Step 3: The request to PSEG Long Island

The utility side of a service upgrade is requested through PSEG Long Island's online portal for upgrading or changing service. According to PSEG Long Island's Upgrade or Change Service page, the utility asks for portal submissions rather than email because of technical problems with emailed requests.

A few points from that page are worth knowing as a homeowner:

  • Your electrician may need to help fill in the technical fields. Most homeowners leave that part to the electrician.
  • PSEG Long Island issues a reference number for the project. Write it down and keep it with your estimate. It is the fastest way for anyone to find your request later.
  • A digital copy of the electrical inspection certificate is required for all new services and service changes. That certificate comes from the inspection agency in Step 5, so the utility side and the inspection side are tied together.

Step 4: Work day, what goes dark and what you need to do

On the day of the changeover, power to the whole house is off while the old service is disconnected and the new one is connected. Plan for it the way you would plan for a storm outage you can see coming:

  • Fridge and freezer. Keep the doors closed and use up anything that will not hold.
  • Medical devices. If anyone in the house depends on powered equipment, tell the electrician at the estimate visit and make other arrangements for the day.
  • Sump pump. If rain is in the forecast and the basement takes water, say so ahead of time.
  • Garage door. Pull the car out first if you will need it.
  • Working from home. Internet, chargers and the home office go down too.

What you need to do on the day:

  • Give clear access to the meter outside and to the panel inside. Move boxes, bikes and stored items away from both.
  • Keep pets inside and away from the work area.
  • Be reachable by phone in case a question comes up.

One part of the job only the utility can do. According to PSEG Long Island's codes and standards forms, contractors may not transfer the service drop to a new point of attachment on the house. If the drop has to move, PSEG Long Island does that.

Step 5: Inspection, certificate and reconnection

Once the work is complete, the approved inspection agency inspects it. If it passes, the agency issues the certificate.

That certificate is what PSEG Long Island needs. Its Upgrade or Change Service page says a digital inspection certificate is required for every new service and every service change.

Keep your copy of the certificate with your house papers. Buyers, insurers and future electricians may ask for it.

When the problem is the meter pan or riser, not the panel

Sometimes the panel inside is in decent shape, but the outside equipment is not. A meter pan rusted through at the bottom, a riser pulling away from the siding, or a cracked weatherhead are all common on older Long Island houses.

All of that is customer-owned equipment under the Red Book, the same as the panel. Replacing it follows the same path: permit, inspection, certificate, and the PSEG request. Our 100 amp meter and riser replacement page describes that job.

Your checklist before the electrician files

  • Know your current service size if you can. A clear photo of the panel label and one of the meter help.
  • List what you plan to add: EV charger, heat pump, addition, new kitchen or a second unit.
  • Find out whether your house is in an incorporated village or an unincorporated part of the town.
  • Be reachable to sign the authorization form if one is sent.
  • Keep the PSEG Long Island reference number once you have it.
  • Plan for the power-off day: food, medical devices, sump pump, car and work.

Need a licensed electrician on Long Island? Call (516) 915-1234 for a straight answer and a written estimate, or request one online. Our office is open 7 AM to 8 PM, seven days.

Need a licensed electrician on Long Island?

Call (516) 915-1234 for a straight answer and a written estimate, or request one online.

Request an estimate